Project Details

Location
BLDG 859 Auditorium Interior Paint
Contract Cost
$73,879.07
Date of Commencement
August 2021
Date of Completion
November 2021
Project Owner
United States Air Force Base (USAF)
Contract Number
FA442721P0111
Type of Contract:
Design Bid Build (DBB)

Project Description

TSI Engineering delivered complete interior renovation of Building 859 Auditorium, executing demolition, surface preparation, and high-performance coating installation in compliance with UFC and UFGS standards. The scope required precise surface restoration, specialty color application, and strict adherence to base safety and fire prevention protocols.

All work was completed within the required 30-day performance period.

Scope Highlights

  • Removed existing wood paneling and trim from walls and window frames (~1,760 SF).
  • Repaired, sanded, and prepared sheetrock for specialty black coating application.
  • Refinished and painted stage wood surface (~31 SF).
  • Prepped, primed, and painted ceiling (~1,584 SF).
  • Installed specialty yellow safety striping (wall and ceiling accents).
  • Performed daily debris removal and site protection measures.
  • Executed work in compliance with UFC 3-120-01, UFGS 09 90 00, and UFC 3-190-06 standards.

Performance

  • Delivered full auditorium renovation within 30 calendar days. 
  • Maintained clean, safe, and code-compliant work environment.
  • Met all federal coating and protective finish standards.
  • Ensured aesthetic consistency across all exposed and visible surfaces.